Marquette Interchange - North Leg
Milwaukee, Wisconsin
Back to Project List
Excavation Support Systems, Marquette Interchange, North Leg, Milwaukee, Wisconsin
Jet Grouting
Project Overview:
Jet grout columns were installed to reduce the permeability and increase the compressive strength of the subsurface soils. The jet grouted elements functioned both as a cut-off and support of excavation wall behind a secant pile wall. Jet grout columns were installed to about 50 feet in depth at five different locations.

    Value of Work Performed:
$1,156,000
Project Duration:
2-1/2 months
Project Completion Date:
March 2006
Project Reference:
Project Owner
Wisconsin DOT

General Contractor
Walsh Construction Company
Gary D. Richards
(414) 933-9688