Crist Steam Plant Unit 7
Selective Catalytic Reduction Addition
Pensacola, Florida
Back to Project List
Jet Grouting

Single-fluid jet grout columns are installed within an active power plant in less than 7 feet of headroom.
Project Overview:
Layne GeoConstruction constructed 500 three-feet diameter, reinforced, single-fluid jet grout columns for foundation support of a new selective catalytic reduction unit. The jet grout columns were installed within a functioning steam power plant, in low headroom and limited access conditions.

The jet grout columns were installed to a depth of 40 feet. The reinforced jet grouted columns were used to create column blocks for new foundation supports, as well as a secant column wall excavation support system.

Load tests surpassed the project requirements, with test results registering 284 kips in compression and 140 kips in tension.

    Value of Work Performed:
$1,100,000
Project Duration:
2 months
Project Completion Date:
December 2003
Project Reference:
Project Owner:
Gulf Power, A Southern Company
Engineer:
Southern Company Services, Inc.
Earth Sciences & Environmental Engineering
Richard M. Franke, PE
Principal Geotechnical Engineer
(205) 992-6224
Geotechnical Engineer:
Jamie Sampieri
(205) 992-5860

LAYNE GEO HOME | LOCATIONS | GEOTECHNICAL SERVICES | SITE MAP | CONTACT US

© 2008 Layne Christensen Company. All rights reserved.