|
|
|
|
|
|
Oak Street Pump Station Upgrade EU-3
Bellingham, Washington
|
Back to Project List
|
|
|
 |
|
|
Jet Grouting
|
|
Overlapping jet grout columns are installed adjacent to the wet well and along the front of the pump station
building for excavation support.
|
|
|
Project Overview: |
|
Layne GeoConstruction installed a total of 72 jet grout columns to depths ranging from 9 to 56 feet, using a
combination of single and double-fluid jet grouting techniques. The objectives were to provide a groundwater
barrier, excavation support, and structural underpinning.
Underpinning the existing pump station was achieved through the installation of 16 columns around the perimeter
of the building. The columns were installed in groups of four, designed for loads of 400 tons. Jet grout columns
were installed as an alternative to piles for the support of the new generator building. Overlapping jet grout
columns were installed along the front of the pump station and adjacent to the wet well. The purpose of the wall
was to provide support of excavation and groundwater control during the modifications to the inlet piping.
Additional columns were installed to provide pipe support at a number of locations.
|
|
|
Value of Work Performed: |
|
$165,000 |
|
Project Duration: |
|
3 weeks |
|
Project Completion Date: |
|
September 2003 |
|
Project Reference: |
Proiect Owner:
City of Bellingham, Washington
Ravyn Whitewolf
(360) 676-6961
|
Engineer:
GeoEngineers
Dan Mageau
(206) 728-2674
|
General Contractor:
Strider Construction
Company, Inc.
Donald Rasmussen
(360) 380-1234
|