|
|
|
|
|
|
|
Valley Creek Sewer Tunnel Project
Soil Stabilization by Compaction Grouting
Bessemer, Alabama
|
Back to Project List
|
|
|
|
|
|
Limited Mobility Grouting
|
|
Compaction grouting is used to stabilize karstic
geology soils in advance of tunneling operations. |
|
|
Project Overview: |
|
Layne GeoConstruction designed and constructed a soil stabilization program in karstic geology along the
alignment of a 10,000 linear foot, 16-foot diameter bored tunnel, at 65 feet below ground surface level.
Initial attempts by the general contractor to advance the tunnel with the tunnel boring machine were
marginally successful in the difficult subsurface conditions parallel to Valley Creek.
Subsequent to the placement of a low slump compaction grout, tunnel production rates increased dramatically.
The compaction grouting process yielded a 500 psi soil block throughout and beyond the tunnel zone. The
grouting virtually eliminated groundwater inflow from the adjacent stream, and immobilized the large boulders
which were present within the tunnel area.
Layne also designed and installed a drilled micropile support system near a large concrete junction box and
72-inch live sewer force main, to protect the utility as the tunneling operations advanced.
|
|
|
Value of Work Performed: |
|
$4,300,000 |
|
Project Duration: |
|
15 months |
|
Project Completion Date: |
|
November 2004 |
|
Project Reference: |
Construction Manager:
Hailey / Rast, JV
Micheal Morris
(205) 425-3272
|
|
|
|
|
|