|
|
|
|
|
|
|
IHNC Lake Borgne Surge Barrier
New Orleans, LA
|
Back to Project List
|
|
|
 |
|
|
Jet Grouting
|
|
Closure piles are installed in jet grouted columns to seal the interstitial space between cylinder piles.
|
|
|
Project Overview: |
|
Layne GeoConstruction played an integral role in the construction of the largest design-build civil works
project ever awarded by the US Army Corps of Engineers. The 1.5 mile long surge barrier project allows the
Corps to achieve a 100-year level of risk reduction in 2011 for some of the Gulf Coast’s most vulnerable areas.
Using state-of-the-art bi-jet grouting equipment and techniques, LGC installed 2,540 3-foot diameter jet grout
columns to depths of up to 105 ft for in-situ treatment of stiff clays and sand fill found throughout the
project alignment using single fluid jet grouting technology. Over 550,000 cubic feet of soils were treated
reaching strengths averaging >500 psi providing support for 18-inch closure piles, which were installed in each
of the jet grouted plumes. The closure pile subsystem provides a means of sealing the interstitial space between
cylinder piles throughout the water column; and together with the jet-grouted soilcrete, provides a means of
mitigating potential seepage and scour below the mud line.
|
|
|
Value of Work Performed: |
|
$ 24,000,000
|
|
Project Duration: |
|
10 months
|
|
Project Completion Date: |
|
March 2010
|
|
Project Reference: |
Project Owner:
US Army Corps of Engineers
New Orleans District
General Contractor:
Traylor-Massman-Weeks, LLC
Construction Manager:
Shaw E & I
Engineer of Record:
Ben C. Gerwick / INCA
|
|
|
|
|
|