Mystic Station Power Plant
High Voltage Duct Bank Project Site International
Independent Energy
Everett, Massachusetts
Back to Project List
Drilled Micropiles
Numerous piles were installed in the restricted access area of an existing switchyard.
Project Overview:
Layne GeoConstruction designed and installed over 5,000 linear feet of 15-ton capacity auger cast piles for support of a new high-voltage duct bank. The piles were required due to the presence of compressible organic soils below the duct bank elevation.

In excess of 150 piles were installed, using the auger cast method, through fill and organics, and into stiff clay. The average depth was approximately 30 feet for the 12-inch diameter piles. Special tooling with a large hollow stem was used during installation to eliminate the necking effect common to this installation technique. One load test was successfully performed in tension to twice the design capacity.

The majority of the pile locations required working off-hours, to coordinate with other contractors on a confined site. Over 50 piles were located in restricted access areas, within an existing switchyard.

    Value of Work Performed:
$450,000
Project Duration:
8 months (intermittent)
Project Completion Date:
June 2001
Project Reference:
Project Engineer:
Washington Group / Fluor Daniel



LAYNE GEO HOME | LOCATIONS | GEOTECHNICAL SERVICES | SITE MAP | CONTACT US

© 2008 Layne Christensen Company. All rights reserved.