Project Overview:
Layne GeoConstruction designed and constructed a drilled tension pile system to tie-down of a highway approach to an immersed tube tunnel roadway. The tension pile design was an alternative to the post-tensioned anchor design provided by the project.

In excess of 580 tension piles were installed to resist hydrostatic forces acting on roadway at 35 feet below sea level. Piles were drilled to depths of 100 to 125 feet through clay, glacial soils and 30 feet into bedrock. The drilled tension pile design load is 315 tons per pile.

    Value of Work Performed:
$6,400,000
Project Duration:
9 months
Project Completion Date:
April 1994
Project Reference:
Project Management Consultant:
Bechtel / Parsons Brinckerhoff
Giovanni Aurilio
(617) 951-6000