South Boston Piers Transitway — Silver Line
Russia Wharf & Fort
Point Channel Tunnel
MBTA Contract E02CN15
Boston, Massachusetts
Back to Project List
Drilled Micropiles
Eighty-eight drilled micropiles were installed to underpin an historic, seven-story building in downtown Boston, in areas with less than 10 feet of headroom.
Project Overview:
Layne GeoConstruction designed and constructed a drilled micropile system for underpinning support of an historic, seven-story building in downtown Boston. The underpinning of the building was integral to subsequent NATM work by the general contractor. The drilled micropile system was installed in areas presenting difficult and limited access, with less than 10 feet of headroom, and isolated pile locations in less than 8 feet of headroom.

The drilled micropiles were installed through urban fill, organics, Boston Blue Clay, glacial till, and weathered rock. Each micropile, with capacities of 85, 132, and 200 tons, were successfully load tested to twice their design values; with the exception of the 200 ton piles, which were tested to 325 tons. In total 88 drilled micropiles were installed to depths of 130 feet.

    Value of Work Performed:
$1,000,000
Project Duration:
6 months
Project Completion Date:
June 2001
Project Reference:
Owner:
Mass. Bay Transportation Authority
Geotechnical Engineer of Record:
Meuser Rutledge Consulting Engineers
(212) 490-7110

LAYNE GEO HOME | LOCATIONS | GEOTECHNICAL SERVICES | SITE MAP | CONTACT US

© 2008 Layne Christensen Company. All rights reserved.